84 GW of RE pipeline held up by grid access delays, transmission gap now a credit risk: Ind-Ra Energy Watch
Renewable Energy

84 GW of RE pipeline held up by grid access delays, transmission gap now a credit risk: Ind-Ra

Ind-Ra says the widening gap between renewable commissioning and transmission readiness is emerging as a key credit risk for the sector

EW Bureau

New Delhi: India Ratings and Research (Ind-Ra) said on Wednesday that renewable energy capacity is being built faster than the grid can absorb it. The agency described the divergence between commissioning and transmission readiness as a key credit risk for the sector.

Follow Energy Watch on X

84 GW awaiting network access

Ind-Ra put the planned renewable pipeline to FY32 at 196 GW. Of that, around 112 GW is still tracking transmission schedules. The remaining 84 GW is waiting on General Network Access (GNA) to be operationalised. Delays on that capacity range from a few months to more than a year. The agency called it a persistent transmission execution gap.

The shortfall is concentrated rather than spread evenly. Key renewable hubs account for close to 42 GW of the delayed capacity, or half the total.

"Risks are increasingly concentrated in a handful of large RE hubs, where evacuation infrastructure continues to lag generation capacity additions, with an average delay exceeding six months. Key RE hubs contribute significantly to the 84 GW capacity associated with GNA delays, accounting for nearly 42 GW of the total.

"This indicates execution slippages at a limited number of substations could materially influence RE integration across India", says Peeush Middha, Associate Director, Infrastructure, Ind-Ra.

32 GW mismatch projected for H2 FY27

For projects due on stream by the second half of FY27, Ind-Ra expects generation to outrun transmission by 32 GW. That figure could rise to 40 GW. The trigger would be a further three-month slippage in interstate transmission system (ISTS) commissioning beyond current timelines.

A project that starts generating before its evacuation is ready has to fall back on temporary general network access (T-GNA). Operating under T-GNA exposes it to curtailment when the grid is constrained.

Ratings holding up, for now

Renewable projects rated by Ind-Ra have not seen material rating pressure from transmission delays to date. The agency credited repayment moratoriums, liquidity buffers and sponsor support mechanisms for that cushion.

Follow Energy Watch on LinkedIN

The cushion is not open-ended. Ind-Ra warned that drawn-out transmission bottlenecks could erode capital structures. Borrowers could end up leaning on sponsors on a sustained basis.

JSW Neo Energy to hold 49% in 920 MW Punatsangchhu-III hydro project in Bhutan

CIL, ArcelorMittal sign MoU to explore syn-gas usage from a coal gasification plant at Paradip

SJVN achieves COD of 75 MW Jamui solar project in Bihar: SJVN CMD

House panel backs MNRE's demand for administrative control over large hydro projects

With no viable HVDC solution at Pang's 4,700 m altitude, inter-state Ladakh GEC project under review: MNRE