DERC approves BRPL's five-site, 97.5 MW battery storage plan for south and west Delhi Energy Watch
Renewable Energy

DERC approves BRPL's five-site, 97.5 MW battery storage plan for south and west Delhi

DERC has given BRPL in-principle approval to set up 97.5 MW/195 MWh of battery storage at five south and west Delhi grid stations

EW Bureau

New Delhi: The Delhi Electricity Regulatory Commission (DERC) has cleared a proposal by BSES Rajdhani Power Limited (BRPL) to install Battery Energy Storage Systems (BESS) at five locations across south and west Delhi, in a step expected to support the capital's shift towards cleaner power. In an order issued on Thursday, the commission granted in-principle approval for the discom to float competitive bids for a combined 97.5 MW/195 MWh of grid-scale storage, officials said on Friday.

More than 2.66 lakh consumers in the two regions are expected to benefit from the deployment, which BRPL has projected will deliver annual gains of over Rs 88 crore. The systems are intended to strengthen grid reliability and deepen the integration of renewable energy into the city's supply, officials said.

Five grid stations, 195 MWh in all

The storage units will be sited at five grid stations: Dwarka (5 MW/10 MWh), Bindapur (15 MW/30 MWh), Hari Nagar (7.5 MW/15 MWh), Sagarpur (30 MW/60 MWh) and Pappankala (40 MW/80 MWh). Officials described the approval as a significant move to bolster Delhi's electricity infrastructure and accommodate the rising share of renewables in its power mix, adding that the facilities would shore up reliability, ease peak-demand stress and allow more efficient power procurement.

The plan marks a shift from BRPL's earlier single-site approach. The discom already operates a 20 MW/40 MWh BESS facility at Kilokari in south Delhi; the new proposal extends that model to a larger, multi-location rollout across five substations.

Tackling 8% peak-demand growth

In its submission to the commission, BRPL said the chosen locations have recorded annual peak-demand growth of roughly 8 percent over the past three years, even as renewable energy penetration on the grid keeps rising. A BESS can function both as a load and as a source — drawing and storing electricity when it is available and feeding it back during periods of high demand — which the discom said improves grid flexibility, reliability and operational efficiency.

Rs 88.35 crore in annual benefits, passed to consumers

BRPL estimated that the project would yield benefits of about Rs 88.35 crore a year over a 12-year operational life. According to the discom, these would stem from energy arbitrage, participation in ancillary services markets, better reliability, deferred network and capital spending, and reduced dependence on costly peaking power.

Follow Energy Watch on LinkedIN

The company told the commission that the resulting savings, including those from peak-load management, energy arbitrage and ancillary services participation, would be passed on to consumers through lower power purchase costs.

AGM 2026: Reliance raises BESS & cell Giga Factory target from 100 GWh to to 120 GWh

Coal gasification crucial for India's energy security, to cut import reliance: Reddy

Centre to review emergency fuel supply curbs as West Asia tensions recede: Official

India's net oil & gas import bill jumps 75% y-o-y to $17.5 bn in May amid West Asia crisis

Exide pursues lithium-ion expansion via subsidiary EESL, retains lead-acid focus