Himachal Pradesh Chief Minister Sukhvinder Singh Sukhu (File photo) File
Power

Sukhu orders faster work on 450 MW Shongtong-Karchham hydro project, targets March-April 2027 commissioning

Himachal CM Sukhu says the Kinnaur project is over 80% complete and will add 1,579 MU a year, targeting commissioning by March-April 2027

EW Bureau

New Delhi: Himachal Pradesh Chief Minister Sukhvinder Singh Sukhu on Monday directed officials to speed up construction of the 450 MW Shongtong-Karchham hydroelectric project on the Satluj river in Kinnaur district, so that it can be commissioned by March-April 2027.

Powerhouse work nears completion

Chairing a review meeting of the energy department, Sukhu said close to 80 percent of the powerhouse construction had been finished.

Work on the barrage will continue through the monsoon, with the Satluj's flow being diverted through bays 4 and 5, while construction on diversion bays 1, 2 and 3 progresses at the same time, according to an official statement.

Overcoming site challenges

Sukhu said the project had crossed the 80 percent overall completion mark despite a series of technical and geographical hurdles, which the state government had addressed through continuous monitoring and improved planning.

Site-specific technical measures were being applied regularly to keep construction on pace, he said, according to the statement.

Boost to generation and state economy

The chief minister said the project would substantially raise the state's power generation capacity, strengthen its energy self-reliance and support environmentally sustainable growth.

Follow Energy Watch on LinkedIN

Once operational, the project is expected to produce 1,579 million units of electricity a year, bolstering the state's energy portfolio and improving grid stability, the statement said. It is also projected to add nearly Rs 900 crore annually to the state economy.

India and Belgium renew renewable energy MoU to cover offshore wind and storage

JSW Energy's operational capacity crosses 15 GW, 60% of which is RE

Buying or not buying Russian crude oil will not end Ukraine war: Dr S Jaishankar

CEA proposes mandatory 10% co-located storage for solar, wind plants commissioned after July 1, 2027

Karnataka plans to scale installed power capacity to 66 GW by 2030: Additional Chief Secretary